Milestones and roadmap
The LokiCheckout consists of numerous Magento modules, each with its own version (following semantic versioning standards) and its own project management. To keep track of changes, the milestones on this page are used.
|
Timeline |
Status |
Goals |
Progress |
Milestone 0.1 |
August 2024 to April 2025 |
completed
|
13/13 done
|
100%
|
Milestone 1.0 |
April 2025 to May 2025 |
completed
|
10/10 done
|
100%
|
Milestone 1.1 |
May 2025 to October 2025 |
open
|
2/20 done
|
10%
|
Milestone 1.2 |
November 2025 to January 2026 |
upcoming
|
0/2 done
|
0%
|
Milestone unscheduled |
- |
upcoming
|
0/1 done
|
0%
|
Milestone: 0.1
Date: August 2024 to April 2025
Status:
open
13/13 done
(100%)
Milestone: 1.0
Date: April 2025 to May 2025
Status:
open
10/10 done
(100%)
Milestone: 1.1
Date: May 2025 to October 2025
Status:
open
2/20 done
(10%)
Milestone: 1.2
Date: November 2025 to January 2026
Status:
open
0/2 done
(0%)
Milestone: unscheduled
Date: -
Status:
open
0/1 done
(0%)
Milestone 0.1 goals
Automated testing via GitLab CI/CD
complete
GitLab project and repositories
complete
Private composer API
complete
Client-side / Server-side filtering
complete
Client-side / Server-side validation
complete
Milestone 1.0 goals
Milestone 1.1 goals
WCAG 2.1 AA compliance
complete
Amazon Pay integration
open
Fedex integration
open
Braintree integration
open
GLS integration
open
Aheadworks Gift Pro integration
open
Amasty Gift Card Pro support
open
BePOST integration
open
Milestone 1.2 goals
Chase integration
open
Braintree support
open
Milestone unscheduled goals
Last modified: June 2, 2025